New CTE Building with additional renovations of existing facilities

Project Details

4200 sf CTE building, including shop, classroom, restrooms and materials storage in addition to electrical and HVAC upgrades of existing buildings.

Project Duration

10 months design, 5 months construction

Completion Date

Summer 2024

Project Cost

$4,681,200.00 Completed $92,000 under budget
Summary

In 2023 IMS was asked to help salvage the floundering Alsea School District GO-Bond projects. We are serving that District as OR/PM on previously contracted projects to upgrade the electrical and HVAC systems and are completing the final elements of construction of a new Career Training and Education (CTE) building.

ALSEA SCHOOL DISTRICT BOND PROJECTS